Pavement Engineering · Applied Research Associates, Inc.
City of Sacramento · RFP R15200801
Interview Briefing · April 28, 2026
Cycle Review · 2022–2025

The pavement reality check

A cycle-over-cycle analysis of the City's pavement program.
Citywide
PCI
60
+1vs 59 in 2022 · target 75
Unfunded
Backlog
$419M
+41%vs $298M in '22
Annual
Shortfall
$121M
$136.5M required · $14.9M received

For every $1 Sacramento spent on resurfacing, the backlog grew by $2.

$59M resurfaced 2022–2024·$121M backlog added·2.05× ratio
Forecast · Reality

Condition held; dollars didn't.

What the 2022 model predicted vs what happened.
Hover any year for detailsActual2022 forecast
PCI · CITYWIDE CONDITION55652023 · NOT INSPECTED60ACTUAL54FORECAST+6 PTS VS FORECASTBACKLOG · UNFUNDED $M$250$450$419MACTUAL$393MFORECAST+$26M VS FORECAST2022202320242025

Forecast missed by 6 pts on condition and $26M on backlog.

District Trajectory

PCI change 2022 to 2025

Citywide PCI held at 60. Four districts slipped.
D3 TalamantesSouth Natomas
+6 pts5662
D1 KaplanNorth Natomas
+4 pts6771
D2 DickinsonSouth Natomas, Del Paso
+4 pts5256
D4 PluckebaumDowntown, Midtown, Land Park
+4 pts6064
D7 JenningsPocket, Land Park
0 pts6060
D8 VangMeadowview, Parkway
1 pt6362
D5 MapleOak Park, Curtis Park
2 pts5856
D6 GuerraEast Sacramento, Tahoe Park
NOW LOWEST IN CITY
4 pts5753
Data Confidence · LowThree flags in the 2025 report
Inflation · 3% to 4%
Drove part of $121M jump
Asset Value · −$360M
No explanation in report
Inventory · −25% arterials
Likely reclassification